Ramp & Bathroom Project - Progress Pictures

Newest to oldest order

April 11, 2026 - National Grid putting a boot over our electric service

 

April 9, 2026 - Verizon technician moving the FIOS line 

 

April 2, 2026 - In the boiler room, a new water meter and copper pipe over to connect with the water service for the entire building

 

March 31 - April 2, 2026 - Relocate the water line outside the area of planned construction

 

March 31, 2026 Gas line inside work done, piped out and inspected,  Ready for National Grid to do the outside gas line move.

 

March 29, 2026 Palm Sunday "Before" pictures, inside and outside

 

 

February 27, 2026 - Old (15+ years) tank hot water heater removed, tankless water heater installed in the main boiler room making space for rerouted water and gas lines to enter the building.

 

 

 